Make Sure You're Running the Latest Version of O3!
If you don't see version number 23.13, please clear your browser's cache and refresh O3.
Needs More Manpower
And tools, and equipment. Users can now import Manpower, Tools, and Construction Equipment into O3.
I Need a NAP
Or a coffee. Either way, we've added the Date Category field to the IWP Nap Rate Chart settings.
This lets you choose between start and finish dates when configuring the the widget.
Not a Clone
When cloning an IWP, we no longer auto create actions (e.g., Auto Created Constraints) on the cloned work package.
Only actions on the IWP being cloned will be copied over to the new work package. Note: status-specific auto created actions will still be created as usual.
That's My Constraint Type
You can now bulk edit constraints from an Entity's Constraints list by clicking on the pencil icon.
This works similarly to bulk editing items in a grid.
Documented
Users can now configure BIM360 folders for Documents, just like Drawings.
Nothing to Hide
We've added a general setting for CWAs that lets you show all Drawings, regardless of the CWP's Contract.
Daily, Weekly, Monthly 4D
You can now change the date axis of the 4D Gantt chart in the model.
This lets you show work package progress by day, week, or month.