Open IWP Constraints by Type Widget

Tags: IWP, constraints, type, widget

Jared Elliott avatar
Written by Jared Elliott
Updated over a year ago

Open IWP Constraints by Type

The Open IWP Constraints dashboard widget provides a breakdown of all Open IWP Constraints, grouped by Constraint Type, and separated into 3 categories:

  • C < 4 - (Red) IWPs associated with these Constraints have a Planned Start Date that is less than 4 weeks away

  • 4 < C < 6 - (Yellow) IWPs associated with these Constraints have a Planned Start Date between 4 and 6 weeks away

  • C > 6 - (Green) IWPs associated with these Constraints have a Planned Start Date greater than 6 weeks away

Need a translation?

  • "C" means constraint

  • "<" means less than

  • ">" means greater than

Clicking one of the bars of the Open IWP Constraints widget will redirect you to an appropriately filtered view of the Open IWP Constraints Tool.